Final Report of “Inspections and Control Project of Moving Pollutions in Year 2009, Nantou County”
Absrtact |
Project Name Final Report of “Inspections and Control Project of Moving Pollutions in Year 2009, Nantou County
Outsourcing Unit Environmental Protection Bureau, Nantou County Government
Execution Unit Hua-Meng Engineering Consulting Cooperation
Project Period 13/04/2009~12/04/2010
Project Amount 7.4 Million NTD
Project Leader Chung-Ching Hsu
Project Manager Chih-Hsuan Chang
Project Staff Ming-Wen Chung、Yen-Wei Liu、Gu-Sheng Lin、Shu-An Huang、Wen-Chieh Chen、Hsin-Yi Bai
Inspections and Control Project of Moving Pollutions in Year 2009, Nantou County” started on April 13, 2009. The execution team finished all items of work in the contract and all were in accordance with the contract. The whole achievements of work from April 13 2009 to April 12 2010 are stated below:
I. Pre-vocational training
Pre-vocational trainings were held to project staffs. By these training courses, project staffs were familiar with every content and job scope of all work so as to excel in this project and cooperate well with each other. In the meantime, this also helped to enhance work quality and achievements.
II. In-Use Motors Testing and Checks Achievements at a Non-Periodical Basis
This Project targeted on in-use motors without doing testing and checks and motors card identification. In total, 20,833 motors without doing testing and checks were given notice. 20,303 motors came and finished testing. The rate is 97.2%.
III. Achievements of Periodical Testing and Service of Outdoor Motor
Finished setting up a moving motor checking stop; Offered suitable locations for far areas, government agencies, promotion activities or to conduct periodical testing and services of outdoor motors for 29 times. The total of service testing is 1,017 times.
IV. Achievements of Noticing Motors without Doing Testing in Official Documents
Every moth, according to the list of motors failing to do periodical testing offered by Agency, the project staffs sent out official documents to those motors. The total documents sent out are 21,251 papers. Among them, 9,272 motors came and finished testing. The return rate is 43.63%.
V. Achievements of Checks and Management of Motor Examination Stop
There are a total of 69 motor examination stops in Nantou county (including the new open M02 Cheng-hsing Motor Stop). In a year, four times of assessment and checking work were finished. Standard
|
---|---|