Project of Year 2009 for controlling and inspecting of stationary sources
Absrtact |
The execution duration of this project is from April 1st, 2009 to March 31st, 2010. The final results of this project were separately introduced as the following:
1. General inspection and on-site examination were executed at 413 institutions. After examination, there are additional of 29 institutions listed in the controlled list.
2. Total of 100 institutions were done with the emission amount examination and data renewal. Insufficient data, unreasonable emission, and institutions which have not been examined in the past three years are prioritized in this examination. Upon completion of examination, the following is found: particles pollutant decreased of 0.618 metric tons, SOx increased 4.894 metric tons, NOx increased 4.697 metric tons, and VOCs increased 46.235 metric tons.
3. Total completion of 100 institutions and there are 56 institutions permits not conforming to regulations with most of the reasons which the facilities are not in conformity with the approved content as stated in the permit (occupies 41%).
4. Aside from Sixth Naphtha Cracking Project, there are 175 permit application received. 98 Installation and Operating Permits were issued after evaluation. Investigations were carried out on time and data establishment upon permit issuance is completed within the stipulated one month period.
5. Through inspection, emission examination, and regulation conformity; this project completed the renewal, maintenance, and expansion of data of 200 institutions. In addition, gas station project reported the examination information of 232 gas stations. Therefore, the database of 432 controlled institutions is maintained, renewed, and expanded.
6. In year 2009
|
---|---|