Hazardous substance monitoring and pollution investigation plan in Pingtung County industrial area
Absrtact |
program is scheduled for work from April 15, 105 to April 14,
The results of the implementation at this stage are as follows:
First, public and private places inventory data collection analysis
Pingnan industrial area tube factory 44 (currently closed 5) and 32 unregistered factories (currently shut down 1); Pingtung industrial area tube factory 36 and no tube factory 108 (currently plant 15 in the industrial area and 22 out of the factory (currently suspended 4); Pingtung processing export area by the tube factory a total of 22 11, a total of 23 unregistered factories; Pingtung Agricultural Science and Technology Park by a total of 13 factories, a total of 34 factories without a tube.
Second, the industrial zone risk potential assessment operations
Pingnan Industrial Zone uses 87 high-risk species of the plant a total of eight factories, 18 processes, which use 11 high-risk species; Pingtung industrial area using 87 high-risk species of the plant a total of plants, a process, The use of high-risk species 1; Neipu industrial area, Pingtung processing export area and agricultural science and technology park is no use of high-risk species of the factory and the process exists.
According to the process risk index calculation method, after estimating the risk potential of each industrial area in the area, it is known that the industrial area of Pingnan Industrial Zone in Pingdong County is a high degree of risk, Pingtung Industrial Zone, Neipu Industrial Zone, Agricultural Science and Technology Park and Pingtung processing export area is a low degree of risk.
Third, perimeter harmful pollutant testing
The project completed the sampling analysis of harmful
|
---|---|
Keyword |
OP-FTIR、FLIR、Canister
|