This project begins from January 12 and ends at December 31, 2017, the completed work items include soil and groundwater testing data related to the previous years. The first monitoring well maintenance work was completed from February to May, and the second monitoring well maintenance work was completed from July to September. After maintenance, the monitoring well conditions remained good. In May, 18 sampling operations were completed during the dry season. One monitoring well (No.1799, Pu-Qiang-Lun paragraph, well number T00216) was sampled due to no water in the dry season until June. During September, six sampling operations were completed .Water quality test results did not exceed the regulatory standards. However, the survey results of underground water quality in the upper and lower half of YanPu area show that the area with the highest level of 1,1-Dichloroethene is still limited to T00414 and T00415, with the exception of T00415-1, which exceeds the recommended reference value . The newly-established TaJen University monitoring well did not detect the 1,1-Dichloroethene concentration after the analysis. It was initially determined that the pollutants did not spread to the downstream. The other on May 19 to complete the sampling and testing company's QA/QC(Quality Assurance/Quality Control) inspection operations, the overall quality assurance content reviewed and amended by the Commission according to the implementation. In addition, the soil regular testing was completed in May. The results showed that the concentration of heavy metal mercury exceeded the monitoring standard of agricultural crops for food crops. The result was N.D(Non-Detection) of the two groups of crops (min bean and chili).
A total of 8 verifications were completed, including soil quality of No. 900 in Zhong-shan paragraph of Chaozhou town, soil quality of No. 33 in Yong-long paragraph of Yanpu village, groundwater quality of No. 556 in XinXing paragraph of Pingtung city, groundwater quality of public wells in Shinkairyo site.Soil and Groundwater Quality of No. 364, 370, 373, 374 and No. Soil and surrounding quality of WanDan township SirAn paragraph. Soil and groundwater quality of Jing-Mao enterprise and Kun-Sheng hardware, soil quality verification operation of FuJu Solar Co., Ltd., of the simple well groundwater heavy metal lead exceeded the regulatory standards, the rest did not exceed the regulatory standards; the team recommended follow-up can be set to a standard monitor wells Jing-Mao enterprises to confirm the situation overweight. The verification operation completed the No. 325 (No. 2) of XingYang segment of XinYuan Township and MingGuang metal factory Co., Ltd. The verification results have been reduced below the standard of improvement, and the PingTung county EPB has released the information according to the verification results.
Emergency response part of the operation is carried out in 7 games, respectively, KanDing township, DingXian paragraph No.322 and No. 329 around the ground, BiaoLiao township, ZhongShan paragraph No. 221 surrounding soil and groundwater, WanDan township, TianCuo paragraph No.1019 around the groundwater, XinYuan township, Xing-Yang paragraph No.391 around the groundwater, ChangZhi township, BaoZiLiao paragraph No.1069 of the ground around the groundwater, LiGang township, TuKu paragraph No.287-58 soil and around groundwater, BiaoLiao township, Dar-Xiang-Ying paragraph two short paragraphs No.12,12 -1, 12-2, 13, 14 around soil and groundwater (each 1 episode), among BiaoLiao township, ZhongShan paragraph No. 221, WanDan township, Tian-cuo paragraph No.1019, XinYuan township, XingYang paragraph No.391 Department of public opinion on the ground stacked slag, after confirmation of the three surrounding soil and groundwater have not been subject to pollution.
For the gas station this year's network application results, the second network abnormalities (PID / FID did not show the relevance) for the Qian-yue gas station and the Qian-yue DongGang gas stations, of which Qian-yue DongGang gas station in 106 years October 25 to complete leak detection and no abnormalities checked. It is suggested that the Qian-yue gas stations included in the 107 annual leak test tube check list. During the year, 13 leak detection tubes were completed. According to the inspection results, there was an abnormal situation in the leak detection tube gas concentrations at the HouBiHu fishing vessel gas station. Therefore, GC-FID (Gas Chromatography-Flame Ionization Detector) analysis was performed on two soil tubes for leak detection, the map analysis showed that only light alkanes were detected, and the rest of the test items were not detected. The pollution potential classification judgment was C grade, so did not trace and only the test results were for reference. Gas station inspection completed a total of 282 times in the first half mainly for written information review, the main missing is incomplete data storage, leaky pipe marking unclear, after counseling, the second half of the review are passed; the second half of the test Leak tube function check, in addition to the RenShouying gas stations found floating oil, the remaining gas leak test tube functions are normal.
In this year, soil and groundwater survey work was conducted for two underground storage tank systems. Soil survey results at Feng-gang gas station were normal. However, the gas stations in RenShouying gas station were immediately subjected to an oil slick test and groundwater surveys, it was found that total petroleum hydrocarbons (TPH) exceeded soil pollution control standards; naphtha and total petroleum hydrocarbons (TPH) of groundwater from simple wells exceeded groundwater pollution control standards. In response to this result, the Environmental Protection Bureau (EPB) has immediately asked the military to initiate contingency measures (removal of residual oil, leak detection, stop leak), while requiring the military to be completed by December 15 of possible contamination or leakage sources survey, December 27 submitted a few days ago necessary measures to deal with the response. The team set up a standard well to the station on November 22, and again conducted sampling and analysis on November 29. The test results showed that VOCs(Volatile Organic Compounds )and TPH did not exceed the regulatory standards. The team will cooperate with the Environmental Protection Bureau to strengthen the station Of the inspections to effectively supervise the handling of its related operations to speed up the control and improvement of pollutants; for the site of soil over the situation, it is recommended that the EPB in accordance with soil and groundwater pollution control law bulletin.
The other with the administrative part of the job, on May 24 to complete the first seminar on remediation technology, June 23 to complete a regulatory briefing on October 12 to complete the second remediation technology seminar; in addition to the implementation of soil and groundwater pollution, there were 5 press releases, 10 technical service consulting, 3 underground gas storage tank system report review, 13 soil pollution assessment survey and testing data Review; and carry out the site inspections 356 times in this year.