Project Name: Chiayi County, the construction of the baseline business waste information and reporting flow and illegal disposal of waste control plan
Project schedule: January 01, 106 to December 31,
Period report period statistics period: January 01, 106 to October 31,
Program funding: Bai Bai 柒 million
The project was implemented on January 1, 2006 in the Republic of China. The main purpose of the project is to prevent illegal dumping by checking the source of waste and assisting with illegal dumping. The report summarizes the summary of the implementation results at the end of October 31, 2006 as of the execution of the plan as follows.
First, business and reuse agencies Waste inspection control operations:
A summary of the work related to the project's auditing of waste by businesses and recyclers is set out below. For details, please refer to "Chapter 2 Waste Inspection Control of Business and Reuse Institutions".
(A) business waste clean-up project book review:
By the end of October, 106, there were a total of 724 supervised enterprises in Chiayi County, and all business institutions should submit the examination and approval rate of waste disposal plan and the annual target of 97% of the examination and approval rate according to law, Under the supervision of the department, there were 315 new deliveries, changes or transaction reviews of waste disposal projects, completed the 100% improvement in the inspection of waste records and reached the target of over 70% of the assessment standards of the Environmental Protection Department .
(B) check check:
The program completed a total of 600 routine examinations with a total of 79 entries, "the actual business online time is later than the scheduled report clearance", followed by "unilateral declaration of unilateral joint declaration after 35 days" accounted for 3 times , The number of cases in which 677 unusual sub-projects were the most unusual was "the lack of output of stockpiles and the storage of suspected short-messages" and the lack of "quality imbalance in reporting", with 561 GPS interceptions being "livestock farms without parked vehicles" Up to a maximum of 574 sub-branches in the field. Among them, 48 were spot-checked for violating the Waste Clearance Law and have been improved after the deadline has been improved. Times, killing dead pig carrying vehicles intercepted 10 times and the EPD case handling of 12 cases, supervise and counseling institutions to make the best use of waste flow to declare the responsibility to complete the improvement of listed companies waste output and temporary storage network Road application rate reached 97% each month.
(C) re-use agencies to check counseling:
There were 63 re-use agencies under the jurisdiction of Chiayi County, of which 3 were approved by the central-purpose regulatory agencies for re-use management and were reused according to the stipulations set forth by the Central-Governing agencies There are 60 management recyclers.
Second, the civil camp to clear the handling agencies check management operations:
As of the end of October, 106, the county has a total of 80 clean-up agencies under its jurisdiction; of which, there are 3 Class A, 64 B, 13 C and 3 handling agencies. The relevant work of the project on the clearance, disposal and clean-up of waste in private civic camps in this project and the review of regulatory work by self-cleaning and disposal agencies are summarized as follows. For details, please refer to "Chapter 3 Management and Control of Waste Removal and Treatment Agency operation".
(A) Waste disposal permit review:
1. Clear Permits Review: During the implementation of the project, a total of 58 applications for removal agencies were reviewed. At present, 37 licensees have been completed and 21 amendments are being made.
2.GPS Verifications: At present, there are 131 vehicles in this POCGT system, of which 9 are Class A removers, 95 are Category B removers, 10 are Category C removers and 6 are recyclers. Ministry, other industry 6. A total of 64 applications for examination applications were filed, of which 12 were initially reviewed, 2 were for basic information, and 47 were renewed. The replacement of 3G vehicles was mainly due to the replacement of vehicle renewals mainly due to 2G withdrawal.
3. Processing Permit Review: At present, there are only three privately owned waste treatment agencies in Chiayi County, namely Class A "You Sheng Enterprise Co., Ltd." and "Class B" and "Law Jie Environmental Protection Co., Ltd." respectively. Among them, "Law Jie Environmental Protection Co., Ltd." from July 20, 102 to August 6, 102 for trial operation, October 25 seized B-level waste disposal agency to handle the permit application, December 09, 102 And January 20, 103 meeting held two review of the permit, on May 21 seized the final draft of the permit, the final law firm issued on June 10, 103 processing permit; "Woo St. Enterprise Co., Ltd. Company "at 102.12.26 Changes in the number of scrap drums and discarded plastic drums the company applied to handle the permissible amount of permits, 103.3.7 Seized and sent a trial operation plan for changing the amount of waste handled and handled it on April 28, Trial operation, 104.10.30 Class A processing license issuance. Another is still handling the license review cases are "Vanadium and Yao Co., Ltd.", "Hop Hing Resources Recycling Co., Ltd." and "Bay Bridge Veterans Hospital" and three.
(B) check check:
The project completed a total of 780 clearings of clearing agencies and found no abnormalities. There were 230 other trips to the site, of which 110 were active ones, 3 were assigned to EPDs, 15 were checked independently, and 102 were checked.
Third, illegal dumping inspection control operations:
Since the implementation of the project, 13 illegal dumping sites under the jurisdiction of the entire county have been patrolled with the illegal dumping case management system for waste every month for inspection of all curated and unregistered disposal sites. A total of 19 related issues such as joint inspection and banning of illegal disposal of waste, banning of work, follow-up on disposal of illegal disposal of waste and follow-up improvement were taken. With the case of environmental health inspection such as 32 cases. Please refer to Chapter IV "Illegal Disposal of Inspection Operations" for the related operational results.
Fourth, business waste assessment and other work
Since the implementation of the project, in addition to actively cooperating with the Environmental Protection Bureau Waste Management Division's assessment of the master project and participating in relevant work review meetings on a monthly basis as required, the "Waste Recycling Zero Waste - Waste Management Performance The score of self-assessment was estimated to be about 25.79 (out of 30, out of a total of 30, of which 95.5% were scores of EPD) up to 31 October, of which the more outdated items were mainly those for prevention of death Illegal flow of pigs served on the number of pieces of information on the punishment. To this end, the next phase of the project will be reported to the Environmental Protection Bureau for reference in accordance with the assessment standards of the EPD in 2006 for reference. In addition, the scoring self-assessment score was estimated at about 9.21 points (out of 20.00 points, of which 6.2 points were EPD scores, about 66.7%). The related activities of "Waste Waste Recycling Zero Waste Removal- Removal and Recycling" Please refer to "Chapter V Work Waste Assessment and Other Cooperation" for the results.