Stationary audit control and air pollution fee repaying plan
Absrtact |
We accomplished 47 permitting documents, 1 has already issued, 2 were still in reviewed period, 2 rejected, 1 cancellation. The average reviewed period is 21 days for installation permit, 15 days for operating permit, and review time coincidence rate is 98%.
After permit issuance, we check 33 processes and 6 not tallied with permit, they all competed the improvement after our notice. We checked 18 plants for its annual
|
---|---|