To the central content area

Air pollution improvement maintenance plan of Jiayi city for 96 year - escape source of pollution examination control plan

Absrtact
Abstract After this year plan starts the execution first to check all previous years not finished work sites, successively the self-management constructs the project air pollution to guard against the system to spend the charge group to obtain builds the project basic document to count 3,610, screening has finished the work site, arranged in order the plumber by a withdrawal bigger project, has the pollution risk of, once receives the populace state one's case, nearby the environmental protection bureau punishment and the air quality survey station the work site primarily. Moreover and to checking (patrols) looks up process of in the control to carry on had not reported to a higher authority the air pollution guards against the system to spend the work site check to raise the newspaper environmental protection bureau charge to check the group to carry on the urging pays expenses. This year total actually does an inspection row tube 820 to build the work site. According to statistical data of construction area of each kind of builds, the total amount is 1,416,622.5 square meters this year. There are several important project in the east, such as The Chia-yi city justice 13 road engineering, the Wen-ya elementary school new-built construction, the Taiwan railroad renews the track structure plan (rebuild project of Niu Ch'ou Ch'i steel beam), rain water sewer project of Wu Fengna Road (second level), the housing new construction in Yunnei, the solvent chemical enterprise department Chia-yi factories and mines site betterment work, etc. Otherwise, in the west there are Chia-yi city will navigation country small 95 year obsolete and the dangerous school building entire constructs the project, develops the spacious forest Shin-ying section 531st sign project the Zhongshan high speed railroad worker forest to Gaoxiong, forever the town motel new construction, the Chia-yi city nurtures the person national elementary school to be obsolete and the dangerous classroom entire constructs the plan project greatly, all constructs limited liability company culture Jin Tsuantien the store housing new construction, Jiayi city Liu places the local first park new construction (first level) and so on. The main sources of pollution attribution in the city are the RC construction, the road engineering and the other projects, accounts for 85.52%, the whole city TSP year withdrawal, therefore key is at for this plan control. Because of some major constructions, including Chia-yi 13 public road engineering, TSP of withdrawal the demolition is 126.58 metric tons, also accounts for 21.5 % Chia-yi city TSP withdrawal. By way of this plan personnel does an inspection and the control, TSP of withdrawal the demolition declines from 589.61 to 272.24 metric tons originally, and the TSP reduction rate reaches 46.17%. Constructs the files work aspect in the information bank to be possible to divide into the copy clerk reference material, the computer file information bank two parts, below separately will pick states explained: First,copy clerk reference material divides into four parts: A. Builds work site material B. Contract unit material C. Sends package of unit material D. Tracing control material. Contract unit and sends material of the package of unit to be pure, separately covers its basic document and its has jurisdiction over or work site of the contract, as for builds the work site material to contain has the basic document, the engineering work time interval data sheet, the pollution checks (patrols) looks up the data sheet and checks (patrols) consults looks up the detailed and so on. Second, correlation of work the computer file information bank Computer file information bank is complex, its covers the scope besides to construct the copy clerk reference material input the files, inquiry, the statistics, the withdrawal the still permissible execution material push estimates and function and so on report form series printing. Moreover, the computer constructed the files still to have the quantity huge electron book, according to control serial number and date integrity establishment computer files. In the guidance work aspect, 2 guidance meeting and 1 explanation can were hold this year, native constructers and governmental agencies were invited. 73 units attended the first meeting and 59 second. In order to reach 150 units in total, one more explanation meeting had hold and 41 units showed up. Finally, the number of person accumulated 173 people, then achievement were carried out to reach as high as 100% (contract number of persons present 150 people of/two numbers of showings number of persons present 173 people). This year goal quality and achieving rate of each work are described with detailed table-1 and chart-1, abstract explanation of achievement of each work is as follows: First, inspect and administrate 820 work sites. Second, ranked constructions based on the policing method, then patrol and inspect those constructions administrated. 2,516 times were completed, and reaches 100.0 % ratio. Third, the work site information bank establishes 2516, each material content includes the work site basic document, present situation work investigation with guards against the system and each time does an inspection to record and so on. Fourth, altogether completes 3 is next the guidance work. Fifth, has completed 20 TSP and sulfur content examination each. Sixth, In this year new declaration row tube 724 work sites, screens 10 work sites to carry on counseling, has completed 10 work sites to implement the experts to scene counselling and the counselling tracing work, and carries on following counselling tracing. Seventh, by checks (patrols) looks up controls scene counselling or telephone tracing counselling reaches ratio of the pollution improvement to reach 100%. Eighth, Checks in this plan does an inspection under the control, because the work site violates the air pollution to guard against the facture to give the punishment to count 12, violates the reject cleaning up law to carry out the punishment to count 19, total accuses punishes 31, at present all completely improved completes, and will strengthen following checks does an inspection to control. Ninth, 96 year this plan the month TSP withdrawal control front row to one’s limit is 589.61 metric tons, truncates the decrement is 272.24 metric tons, the reduction rate reaches 46.17%. Tenth, This city builds the project air pollution to guard against the system to spend always reported to a higher authority the number of articles is 724, reported to a higher authority the amount total 5,9.71,162 million Yuan, have given 6,6.51,317 million Yuan, deducts draws back the expense 1.97,617 million Yuan, equals the actual receipt amount is 6,4.53,7 million Yuan. East of this city the area work site to gives the proportion high to have 127%, but is higher than 100% reason to giving rate to have to make up for the spatial dirt expense for the partial architectural engineering after the settlement, down to the actual receipt amount is higher than the declaration amount. 11th, this year reported to a higher authority in the work site screens 6 to guard against a system measure finer work site, carries on the evaluation work, has completed 6 work sites experts to the scene counselling evaluation, and screens 3 environmental protections fine work sites. 12th, this plan carries out the result for the promotion, this city work site carries on fence the green beautified aspect, this year altogether completes counselling fence green to beautify 39, including 15 work sites executions fence advertisement, 2 work sites molds the work site characteristic by fence other colored drawings on pottery, carries on promotion the work site green beautification, some 21 work sites plant the flowers and plants way to carry on the green beautification, 1 plants the flowers and plants way and the union advertisement carries on the green beautification. 13th, this plan altogether continues to carry on checks and counsels 16 spent clays not to fall to the ground the work, traces its following backfill one after another, lays down the condition total to do an inspection to trace 26, and takes demonstration other work site, reaches result of the comprehensive promoted, future will counsel the owner to counsel changes by CLSM (plastic low intensity) the grouting replaces the backfill folk recipe, maintains the path environment quality. 14th, this plan total counsels completes 36 work sites to carry on the construction now and then finishes when the partial exposed vegetation afforestation, amounts to work site of its afforestation vegetation area the execution afforestation method to reach 42855.66m2.
Keyword
construct engineering,Escape source
Open
top