英文摘要 |
The current executive term of this program was from 2010/04/01 to 2011/03/31, during which every quantitative task has fulfilled the requirements of the contracts. The contents and results in details of the related operations are elaborated in the sections of this report.
1.Permit review practice
Till 2011/03/31, the County registered 351valid installation permits and 937 valid operation permits. During the program execution, a total of 306 processes were permitted after the monitoring and test on 213 fume channels and 56 perimeters. On-site monitoring found 10 fume channels and 1 perimeters with anomaly, largely because the sampled facilities have failed to be inspected as scheduled. In every of these cases, the monitoring and testing persons have noticed the on-site sampling persons from the inspecting institution to stop sampling and requested the factories to give written notice of re-inspection on a later date. Also, of 453 pre-issuance on-site inspections, 72.8% complied, with 123 processes non-complying with the contents of their applications, representing 27.2% noncompliance, which was lower than 39.1% of 2007 and 67.31% of 2008. This indicates that the firms have been increasing in quality under reinforced audit and control over the years to comply with the requirements of the Bureau of Environmental Protection.
2.Permit inspection practice and follow-up
A total of 453 processes were inspected in 324 cases with noncompliance found in 123 processes, representing 27.2% noncompliance. A total of 74 noncompliant processes were in this county except Changhua Coastal Industrial Park (22% noncompliance out of 338 inspections) and 49 noncompliant processes in this Park (43% noncompliance out of 115 inspections).
3.Management of regular inspection & report
Completed the monitoring and inspection on 62 fume channels. Nine cases were found noncompliant. Inspections with written notice in the noncompliance after thorough improvement were completed.
4.Inspection of stationary pollution source
(1) Completed the inspection on the regulatory compliance of 61 firms in this county that are in the speculated industrial category.
(2) Completed the test for heavy metals on 10 fume channels, all satisfying the standards for emission.
(3) Completed test for flue or perimeter on 20 fume channels or perimeters, of which
The value of steady abundant agronomy science and technology examination is 78, surpasses the laws and regulations standard at 50, and fined for NT$100,000. For glory fine enterprise Limited liability company, its sulfur oxide compound surpasses the emission standard and accuses legally.
(4) Completed the test and analysis on liquid fuel at 30 factories, of which new Wen the Qin hardware enterprise limited liability company clear shore factory including the sulfur share is 1.4%, surpasses the laws and regulations announcement standard at 0.5% and accuses legally
5.Collection of air pollution charge
Presently, 826 firms in this county are facilities that should report air pollution charge. The information bank control program according to the spatial dirt, from the year 99 1st season to year 99 4th season, spatial dirt Fei Jiandang and the examination finish rate is 100%. The assistance examines and issues after investigation totally 3 from the factory coefficient, the spatial dirt spends the network declaration rate promotion to 88%.
A total of 452 factories were reviewed in respect to air pollution charge; 160 cases of SOx. NOx
were found correct in reporting the air pollution charge, which represented 35% of the case reviewed.185 cases of VOCs were found correct in reporting the air pollution charge, which represented 43% of the cases reviewed.
In total of 64 factory volatile organic matter, 13 kinds of individual species were checked and reported that certitude 15 times, occupy checks 23%th number of articles.
6.Results of on-site inspection in fugitive particular matters of stationary source
At present, granulated substance quarry total 8th in this county row tube and transport business.
The granulated substance quarry path washes sweeps the accumulation course number is 8,843.5 kilometers, achieves TSP to reduce to 122.04 metric tons and PM10 reduces to 22.99 metric tons.
The County controls 152 firms as stationary source of fugitive particular matters. This program carries out on-site inspections pursuant to the “Deficiency marking and treatment principle for violation of the regulations on air pollution preventing facility of fugitive particular matters” announced by EPA.
7.Creation of database
Completes the various pollutant discharge first 20 greatly altogether 50 checks, the clear shore industrial district expands the row tube 20 factories and the information bank maintenance renewal work.
8.Completes 10 factories and 5 food and beverage industries counseling work.
Carries on the counseling work, most of manufacturers can accept the counseling opinion. Coordinated the improvement opinion regards to the management stratification plane. The equipment and the system regulation improvement involves the manufacturer transport business consideration. this part had still not completed. Another food and beverage industries counseling manufacturer coordinates the improvement opinion and revises its operating mode and the lampblack emissions questions. The manufacturer has not suffered again after the consultation.
|