The project of Evaluation of Natural Treatment Sysetems (NTS), 2011 executed from May 16, 2011 to December 31, 2011. Contracted working items are summarized as follows:
I. For operation and maintenance of the NTS sites patrol work.To December 23,2011, for program management of the four sites for a total of 104 patrols, including lack of supervision to improve submit a total of 65 times. However, one can not improve its natural purification facilities because Huo-Shaso-Ping has been officially stopped functioning on June 11,2011, ecological landscape pool dried submit current can not be improved, such as follow-up after completion of construction inspection to confirm.
II. The maintenance of the site clearing, to December 23,2011. maintain the site within four natural purification in plants has been completed remove the replanting of a contract. Another part of the plants harvested twice a plant site have been completed harvesting operations, statistics, the total amount of 14,891 kg removed.
III. The natural purification of various water quality sampling and analysis, plan implementation to December 23,2011. Three natural sites for the purification of water six times, respectively, perform sampling, sampling date for May 23, June 28, July 16, August 31, October 16 and November 10, and according to water quality test results for water quality improvement benefits of the site assessment work. Huo-Shaso-Ping site water quality sampling done four times, and the remaining communications business, and success of Lotus Park, Hing Yan reservoir catchment point into the flow point of 28 samples were completed
IV. Complete the Hong-Lo natural purification facilities and North-Eastern converging entrance of the reservoir non-point spot natural purification facilities, seasonal ecological surveys and data archive.
V. Water quality sampling and analysis of Nation Penghu University and Penghu Prison, the current two sites four times the water quality sampling and analysis to complete the job, and functional assessment of the efficiency analysis.
VI. For EPA assessment, the site contains natural purification facilities to check and assess the success of the reservoir, the natural purification facilities in August 25, perform on-site audit work, check the project status including description of maintenance management environment , operating manuals and records complete, operational problems and lack of counseling. The river examine, check the reservoir related issues, information submitted with the current operation to check. On October 11, successful completion of the reservoir to check the program to assist in information exchange and the whole presentation; for information exchange with various units and catchment water quality and quantity throughout the investigation.
|