環境資源報告成果查詢系統

101年度烏溪(大肚溪)及濁水溪河川揚塵預警、通報及宣導計畫

中文摘要 本計畫執行期程自101年7月13日至102年7月12日止。各項工作均於預計期程內完成。每季蒐集烏溪(大肚溪)及濁水溪河川圖資及配合現場巡查作業,瞭解河川裸露地分布面積及變化情形,並針對本縣河川及空氣品質特性,制定「河川揚塵緊急應變標準作業程序」,完成建置預警、通報及回報資訊平台,以自動化方式監控河川揚塵懸浮微粒濃度,當達到設定濃度時,由資訊平台自動發送簡訊及電子郵件以進行預警通報。本年度為加強民眾及中央地方各單位橫向聯繫,共辦理4場次教育宣導活動、4場次實地演練及2場次防制業務聯繫會議,並制作30秒宣導短片於本縣有線頻道內託播2個月,以增進縣內民眾對河川揚塵的認知及防護。此外,本計畫於揚塵好發季節期間於揚塵影響鄉鎮內進行環境清理作業,共執行4201.7公里,可削減PM10量達10.92公噸。
中文關鍵字 烏溪,濁水溪,河川揚塵

基本資訊

專案計畫編號 經費年度 101 計畫經費 5870 千元
專案開始日期 2012/07/13 專案結束日期 2013/07/12 專案主持人 曾厚元
主辦單位 彰化縣環境保護局 承辦人 巫素專 執行單位 新系環境技術有限公司

成果下載

類型 檔名 檔案大小 說明
期末報告 期末報告定稿.pdf 39MB

Warning, announcement and promotion of the fugitive dust along Wu River and Zhuoshui River in 2012

英文摘要 The execution schedule of this Plan is from July 13, 2012 to July 12, 2013, and each job has been successfully completed within the scheduled time. In each season, we collected the river-related drawings of the Wushi River (Tadu River) and Juoshui River and conducted a relevant field patrol inspection in order to understand the distribution size and changing status of the exposed river area. In addition, we also compiled the “River Dust Diffusing Emergency Response SOP” according to the characteristics of the rivers and air quality in this county. Based on the said procedure, we completed the implementation of a pre-alarm, notification, and information report platform for monitoring the density of the river dust diffusing suspensions by automatic method. When reaching the set density, the information platform will transmit the text and e-mail automatically to execute the pre-alarm notification function. To reinforce the horizontal communication between the folks and the competent local authority, this year we sponsored 4 rounds of education/dissemination activities, 4 rounds of field exercises, and 2 sessions of prevention operation communication meeting. Further, we also produced a 30-second dissemination film and it has been broadcasted on cable TV for 2 months in this county with a hope to enhance the folk’s recognition and protection for the rive diffusing dust. In addition, we also launched the environment cleaning work in townships affected by the diffusing dust during the booming season of dust diffusion. In result, a length of 4,210.70 kilometers was executed and it is expected that some 10.92 tons of PM10 could be reduced.
英文關鍵字 Wu River,Zhuoshui River,Fugitive dust