(A) indoor air quality operations
The inspection work for the second batch of premises has been carried out. In the venues such as XiuTai Cinema, Yazhi Hall, Er Xin, 805 Hospital and a letter, there are over-standard situations. The project was started in October with the guidance of interior space experts and scholars. Combined with 106 years of innovation as a 24H test, unqualified and close to the standard value of the unit please experts and scholars to provide suggestions for improvement.
(B) air quality monitoring station operation and maintenance
To maintain the normal operation of the air quality artificial stations (3) and automatic stations (2) within the jurisdiction of the county, so as to complete the secondary release of TSP, PM10, PM2.5 and falling dust from the three stations of the artificial station Maintenance work; part of the automatic station also completed 2 regular monthly secondary maintenance, data availability rate of 98%.
1, manual station operation and maintenance operations and monitoring results
TSP, PM10 and PM2.5 samplers in three artificial stations under normal operation and regular maintenance work carried out a total of 24 regular maintenance work as of the end of December, 106, without any temporary failure and requiring overhaul The situation and implementation of multi-point correction and maintenance on a quarterly basis.
2, automatic station operation and maintenance operations and monitoring results
This year's plan requires monthly secondary maintenance. As of the end of December, 106, the team conducted a total of 24 routine maintenance work on the monitoring equipment of Fenglin Station, and carried out annual maintenance and calibration of automatic station on a quarterly basis. During the implementation of this project, the availability of data from January to December in Fenglin Station reached an average of 98%. The monthly data collected from automatic stations was completed on schedule. The data of Fenglin Station was uploaded to the EPD website in December.
3, the local characteristics of the effectiveness and results of PM10 and PM2.5 control or research work
Complete the PM10 and PM2.5 particle concentration and its water-soluble ions and carbon species composition analysis once, the results will be collected in February next month after submission to the Environmental Protection Bureau for future reference, the current information has been updated to December 106, the current year PM10 and PM2.5 related regulatory or research work from the Han Technical College Station, the city health station as a designated station, the implementation of PM10 and PM2.5 suspended particulate concentration and chemical composition (water-soluble ions and carbon species composition) analysis, the relevant regulatory or The research work has been independently written into a report for the PM10 and PM2.5 analysis results.
(C) Green landscaping, air quality purification area
1. In order to extend the pollution purification work, this project assists Hualien County Environmental Protection Bureau in promoting the inspection and counseling of air quality purification areas this year and finds that lack of supervision urges management units to improve and assists more towns and townships to apply for blank products Purification zone, in order to maintain the good air quality in the county as the goal. Completed a total of 23 inspections of empty space in the county clean-up operations, investigation of 8 carbon sinks of which 2 with the specialist, primary and secondary education and propaganda for handling 4 empty product purification area on-site assessment operations.
2. The county reported 2 corporate adoption in 23 air quality purification zones and 2 adoption by NGO units in the EPD's "106 Selection of Good Adoption Units for Air Products Purification Zone". With the efforts and cooperation of all the units , The county adopted unit won the award 3.
(D) electric car-related business
This project is based on the contract specification content, quarterly against the jurisdiction of the charging station (58 stations) inspection, maintenance and charging station part of the power consumption inspection. Until December 106, the first to the fourth quarter of the charging station has completed the inspection, maintenance and power consumption inspection operations, all stations are functioning.
(E) continuous monitoring system for flue CEMS
According to the contract specifications, the project will conduct CGA, RATA, OP, potential and signal comparison, on-site inspection and other checking operations of the top five factories in the county (TCC Heping Plant, Taili Hualien Plant, Asia Cement Hualien Plant, Heping Power Plant and Zhonghua Pulp Mill) , 10 projects of CGA standard gas inspection were completed in 106 years; 25 RATA supervision and inspection operations were conducted; 50 sub-inspections were conducted regularly to inspect OP operations; and the percentage of effective monitoring hours was over 85% of the regulatory standards.
(F) publicize the briefings and meetings
1, self-management of indoor air quality advocacy briefings
Invited the Environmental Protection Department of the Environmental Protection Department as a lecturer to target 100 people in charge of the first and second batch of public announcements on regulatory announcements with reference to the auditing standards, procedures, improvement methods and penalties, and how to implement indoor air Quality self-management mechanism, so that all units and agencies can pre-make indoor air quality management.
2, empty product purification area management and indoor plant propaganda briefing
At the meeting, all bureaux and offices in towns and counties and township government offices in the county and municipality were invited to set up relevant staffs and contractors for the maintenance units of existing free-space areas. A total of 90 participants attended the seminar on March 30, Encourage and urge Township, Town and Township Offices to submit project proposals and supervise the maintenance and management of existing air quality purification areas, as well as help enhance the quality of air quality in public environments Concept.
3, CEMS connection instructions
A briefing session will be held so that each connection factory understands the importance of continuous automatic monitoring and its relevant laws and regulations to be followed in order to establish the normal functioning of the continuous monitoring and connection system of flue in Hualien County and ensure the CEMS data Correctness
4, indoor air quality inter-bureau meeting
Indoor air quality management laws related to the management of the premises, the Authority and the unit can first understand the current EPA's indoor air quality planning, and by the Environmental Protection Agency to explain the relevant authority and responsibility of each unit to establish the relevant Bureau of Hualien County government horizontal contact Window to facilitate the grasping of the implementation of the indoor air quality ordinance and to prevent the offices from immediately responding to the policies to be implemented by the EPD after the announcement of the control list has been released. Another contact information in the contact window and some renewal of the list of 105 years.
|