107年度臺南市營建工地污染管制查核計畫

中文摘要 經統計,計畫執行期間營建工程申報開工案件計有7,923件,申報開工案件的空污費繳納總金額為255,937,584元;完工結算案件共計6,303件,總退費金額為18,413,476元、總補繳金額為31,648,928元;另外有1,091件工地因逾期申報而遭加徵滯納金,所加徵總計金額為2,063,543元。而統計上述相關金額後,整體營建空污費總淨收金額為308,063,531元。另在網路雲端系統使用率方面,使用網路申報比例為27.5%,雲端下載繳款單比例為71.53%,而整體網路雲端系統使用率為99.04%。 工地管制方面,施工中工地共有12,151處,執行19,370處次工地巡查,納管9,810處,納管率為80.73%;工地查核法規符合率為91.81%,其中一級工地為88.79%、二級工地為95.31%。至於工地污染產生量(TSP)總計為22,996.76噸,巡查納管22,079.18噸,污染量納管率96.01%,經污染管制後的排放量為8,353.74噸,污染削減率為63.67%。
中文關鍵字 107年度臺南市營建工地污染管制查核計畫

基本資訊

專案計畫編號 EPA-107-L001-30-202 經費年度 107 計畫經費 1870 千元
專案開始日期 2018/03/30 專案結束日期 2019/03/29 專案主持人 王應堂
主辦單位 臺南市政府環境保護局 承辦人 呂政霖 執行單位 堃捷工程股份有限公司

成果下載

類型 檔名 檔案大小 說明
期末報告 107營建(全文).pdf 49MB

The project is “2018 Tainan City’s Construction sites Management and Inspection Project”

英文摘要 The project is “2018 Tainan City’s Construction sites Management and Inspection Project”, which executed from 30 March 2018 to 30 March 2019. During the period, there were 7,923 new construction sites declared the air pollution control fees, collected a total amount of NT$ 255,937,584.The 6,303 cases of completed-contract construction sites with NT$18,413,476 in overpayment refunds NT$ 31,648,928 in total repayment. Besides, 1,091 cases of construction sites were an overdue declaration of air pollution control fees and been added delinquency charges to any amount not paid after the deadline. Over 1,091 cases had been imposed upon interest fee that did not pay within the deadline and over 30 days, a total amount of NT$ 2,063,543. Follow the above construction sites declared the air pollution control fees, which totaled NT$ 308,063,531. In addition, in terms of cloud system usage, the internet applying ratio is 27.5%, the payment notices ratio of internet cloud download is 71.53%, and the overall cloud system usage rate is 99.04%. In terms of the safety inspections in construction sites, there are 12,151 sites under construction and 9,810 construction sites have been included within the inspecting management, and control rate was 80.73%. With respect to conformity rate 91.81% rached acceptable levels of regulatory compliance construction of the first category was 88.79% and the second was 95.31%. The estimated TSP(total suspended particulate) emission of construction sites was 22,996.76 tons. After through the project’s management, the actual TSP emission downed to 8,353.74 tons, which shows that emission reducing rate was 63.67%.The project conducted the 81 construction sites in total among of 39,040-kilometer street sweeping and washing. Promoting 2,022m2 green construction fence within 17 construction sites and 54 construction sites covered by 358,675m2 straw mats. In the control of open-burning straw,there were still 58 sites occurred straw open-buring that burned 13.97 hectares. The project’s members assisted to extinguish a fire on 2.14 hectares,and the proportion of burning in total cultivated area was less than 0.1%.Then, the project made “Non-Open-Burning Article” agreement with 253 contracted farmers among 4 rice manufacturing associations, total rice paddy reached 1,132 hectares.However, the project held 5 small-scale public communication activities, and published news ticker and visted 120 chiefs of Village to boradcast. Moreover, the project conducted the barren land investigation and consulting improvement, total of 48.73 hectare, including 22.03 hectare of normal barren land and 26.7 hectare of river barrren lands. The objective of the plan is to mitigate the emission of air pollutants produced from burning joss paper and incense during Ghost Festival and temples major festival in Tainan. The major way we conducted the policies named “Reduction of Joss Paper” and “Concentrated Burning of Joss Paper”; moreover, the project held 1 division meeting and 5 explanation session,then visited 10 collective housing coordination.Meanwhile, the amount of concentrated-burning joss paper was 575.38 tons, gathered form 594 times. On the other hand, we promoted “Donating-replace-joss paper” project, cooperating with charitable organizations. There were 4,586 people taking part in this project by donating money, contributing approximately NT$ 2,696,271.
英文關鍵字 The project is “2018 Tainan City’s Construction sites Management and Inspection Project”,