環境資源報告成果查詢系統

108年度嘉義市逸散污染源稽查管制計畫

中文摘要 營建工地作業中會產生揚塵污染問題,常引起民眾陳情及抱怨,且其所排放之粒狀污染物,佔固定污染源粒狀物排放量的比例高,須加強重視;另有營建工地噪音問題,亟待進一步解決及改善。計畫執行營建工程污染管制,計2,115處次稽巡查作業,其中未符合規定之營建工地計138處,皆已進行輔導並改善完成。有關營建工程之污染物排放削減部份,污染物削減逸散粉塵削減量為573.60公噸、TSP 削減量為160.03公噸、PM10削減量為88.91公噸,削減量達總排放量52.09%。另外針對區域開發、疏濬工程或排放量大等營建工程,輔導裝設CCTV 7處。辦理揚塵空污陳情案件35件,經由稽查人員現場輔導後完成改善。舉辦2場說明會,以加強輔導營建業者空氣污染防制及營建噪音防制;並輔導工地使用環保綠建材9處,使用環保油漆14處。在工地綠美化部分,推動營建工地實施圍籬綠美化共52處,其中圍籬植栽綠化計13處。另輔導營建工地認養道路23處,推廣工地張貼道路洗掃電話專線25處,洗街及掃街長度共計4,228公里。有關營建工程噪音稽、巡查作業部份,營建工程噪音主動巡查及陳情稽查計365件,完成調查施工機具計55件,包含機具名稱、品牌及型號;與辦理噪音陳情案件65件,經由現場輔導後,皆已改善完成。
中文關鍵字 營建粉塵逸散、營建噪音

基本資訊

專案計畫編號 1071296 經費年度 108 計畫經費 2690 千元
專案開始日期 2019/03/05 專案結束日期 2019/12/15 專案主持人 王志文
主辦單位 嘉義市政府環境保護局 承辦人 許智輝 執行單位 創境科技有限公司

成果下載

類型 檔名 檔案大小 說明
期末報告 108年度嘉義市逸散污染源稽查管制計畫(全).pdf 23MB 108年度嘉義市逸散污染源稽查管制計畫(全)

2019 ChiaYi City fugitive emission sources audit control plan

英文摘要 The dust pollution problem caused by construction site is generally existed in crowded urban area and usually results in public petition and complaint. In addition, the percentage of particle pollutants discharged from constructions is extremely large in the stationary particle matters pollution and it is desperate for further resolution and improvement. Meanwhile, the environmental issues arising from construction site also include the noise. To promote the life quality of citizens, it is necessary to improve the air quality and noise problems in Chiayi City. This project implements construction pollution control by means of 2,115 audit patrol. Among the audit results, 138 construction sites not compliance to laws and regulations were found and the counseling was conducted and traced to the completion of improvement during the project implementation period. Aiming at the reduction of pollutants discharged from construction sites in this city, 573.6 tons of fugitive particle pollutants were reduced, the TPS reduction was 163.03 tons. PM10 reduction was 88.91 tons, and the overall reduction was 52.09% of total emission. In addition, the CCTVs were installed aiming at 7 regional development, dredging or constructions with large emission. 35 dust pollution petitions were managed and completed of improvement via counseling of auditors on site. There were also 2 conferences to reinforce the counseling of constructors in respect of air pollution prevention and construction noise control. The project further assists 9 construction sites for using environmental construction materials, 14 sites using environmental paints. As to the greening, 52 fence greenings were established on construction sites. Among them, 13 were plant fences. 23 construction site road adoptions were assisted. Road washing and sweeping hotline was posted on 25 construction sites, total length of road washing and sweeping was 4,228.416km. As to the audit and patrol of noise from construction sites, 365 active patrol and petition audit aiming at noise of construction site have been implemented. The survey of 55 construction equipment, including the name, brand and model of equipment were completed. Among them, most frequently used item was excavator, total in 36 items. 65 noise petitions were managed and they were all improved via the counseling of auditors on site.
英文關鍵字 fugitive emission sources audit control