English Abstract
The summary of the implementation results of the various tasks of this project is as follows:
(1) Promote the licensing control system
This year, 20 applications were filed for license cases, including 1 application for license installation, 1 application for operating license (new design), 4 applications for operating license (transition 2nd version), 10 for license extensions and 4 for changing and reissuinghe basic data of the operating permit. The average number of review days was 4.5 days, which all met the legal deadline (30 days). In addition, in order to effectively implement the licensing system, 26 license inspections were performed. Except for 1 public and private place, 1 license due to the death of the person in charge, without changing the person in charge, and the designated agency was missing, and the other with regulation compliance were 100%.
(2) Inventory of fixed source listing data
At the present stage, a total of 79 inventory management data have been checked, and the work achievement rate is 100%. After the update, there are 253 public and private places under the management of fixed pollution sources in Chiayi City. According to the statistics of the fixed pollution source database after the completion of the establishment of the archives, the air pollution volume under the jurisdiction after the update of the process pollution emissions includes particle pollution 19.19 tons/year, sulfur oxides 17.52 tons/year, and nitrogen oxides 107.957 tons/year, volatile organic compounds 134.88 tons/year, and carbon monoxide 29.23 tons/year.
(3) Collection and verification of air pollution fees
In terms of air pollution fee collection, the air pollution fee collection review was completed from the first quarter of 2019 to the fourth quarter of 2019. A total of 88 public and private places were listed in the air pollution fee, and the average declaration rate and payment rate were 100%. Among them, the actual amount collected in 2019 was $NT 1,196,055; the first quarter to the third quarter of 2020, the three-quarter settlement received was $NT 670,793, because there are still 26 places not declared, which was with incomplete information so it was not included in the analysis.
In terms of air pollution fee verification, 40 cases of sulfur oxides and nitrogen oxides were completed, 40 places of volatile organic compounds were verified, and 41 places of particulate matter verifications were completed with the operation achievement rate 100%.
The Solvent Chemistry Division of Taiwan Petroleum Co., Ltd., which is a major source of VOC pollution in this city, has been performed equipment component inspections with 4,500 points. According to the results of inspection and sampling, the leakage concentration value of 0-5ppm accounts for the highest proportion, about 99%, totaling 4,488 points. At 5.01ppm~1,000ppm, it’s about 0.5%, 6 points in total, and the leakage concentration value between 1,001ppm~10,000ppm, it’s about 0.5%, 6 points. The results of the overall sampling test are all lower than the defined value of 10,000 ppm for leakage. Among the 4,500 sampling points, the sampling results were in line with the air pollution fee declaration situation.
(4) Inspection operations
At this stage, 609 inspections have been completed. Among them, 305 inspections were conducted mainly for inspections in areas with large pollution emissions and in line with EPA emission plans or subsidies, such as the petroleum refining industry, gas station industry, and hotel industry. The current inspections of the factories are in good condition. Among the 304 audits, 31% of the audits were reported as the highest, followed by active audits with 25%.
(5) Fixed pollution source permit and air pollution fee promotion briefing
There has been one law advocacy meeting related to fixed pollution sources held and it focused on the refined differences in the latest air pollution regulations. The content is to add new violations of the air pollution control law (especially related to the discharge of harmful air pollution, during the deterioration period of air pollution, poor air quality areas with serious air pollution situation), and the revised boiler air pollutant emission standards have been comprehensively tightened (should comply with the new system since July, 2020). A total of 91 units including public and private places with permits, air pollution charges, and the escape of particulate matter in the Chiayi City were invited. A total of 46 units attended this meeting, with 46 participants and the attendance rate was about 50%.
|