英文摘要 |
To effectively guide the fugitive dust pollution generated during the construction of construction projects, this plan promotes the active implementation of pollution prevention work on construction sites using graded inspections, counseling large construction sites, and project control areas. During the project period, a total of 4,585 cases were completed. The emissions from inspections reached 90.6%, and the compliance rate of construction site management measures was 82.2%.
There were 2,837 air pollution fee declarations for construction projects, and the levy amounted to NT$61,320,505. In terms of air pollution fee auditing and reporting, a total of 58 construction declarations were overdue, with a total late payment fee and interest of NT$21,951. There were 379 cases, with a total of NT$370,717 in late payment fees and interest. There were 48 undeclared projects in total, of which 25 were declared and paid for air pollution fees for construction projects. The amount collected was NT$2,513,656. The net amount of air pollution charges is NT$80,650,474
A total of 4,585 inspections were carried out and 130 inspections were assisted, with an average emission ratio of 90.6%. 2,633 construction sites were inspected during construction (the total number of inspections was deducted from 1,270 unconstructed and 682 completed settlement confirmation cases), and the inspection signature rate was 87.9%. On February 3, 110, and April 19, 2011, he assisted in the implementation of the construction project's empty product deterioration response once each (Dongshan Station) and uploaded a total of 9 strain records to the EPD (7 construction sites). The inspection and management rate of newly declared construction sites was 74%, and the compliance rate of the overall management measures and regulations was 82.2%, of which the first-level construction projects were 82.6% and the second-level construction projects were 81.9%.
Conduct 30 large-scale construction site counseling every month. During the implementation period, 77 construction sites have been coached (360 times). With the help of homework, 47 construction site counseling has been improved.
Inspection and guidance of 3 project control areas, Jiaoxi area has a total of 8 construction sites, the compliance rate is 75%, and the pollution reduction rate is 68.1%; Yilan urban area has a total of 14 construction sites, and the compliance rate is 71%. The pollution reduction rate was 53.6%; there were 15 construction sites listed in the Lize area, the compliance rate was 73%, and the pollution reduction rate was 61.6%. The overall area control compliance rate was 73%, and the pollution reduction rate was 57.5%.
A total of 21 construction sites were unearthed and tracked under the execution of construction projects, including 17 first-level construction projects and 4 second-level construction projects, of which the road contamination level was upgraded from C to B to 9, and from B to B. Class A has 12 locations.
The dredging project transport vehicle body is pulled down to cover 15 cm of photography track. The total number of photography vehicles is 403 vehicles. The number of vehicles that comply with the construction project management method and the fixed source fugitive management method has 402 vehicles. The rate is 99.8%.
A total of 328 inspections have been made for 101 pipeline projects, 244 of which are 0 points and no missing points, 49 times of missing points between 4 and 8 points, and 35 times of missing points with more than 10 points.
There are 120 noise measurements in total, including 84 first-level construction projects and 36 second-level construction projects. The measurement results are all in line with the daytime control standards. Among them, 8 were measured in the second-level control area, and the third-level control area was measured at 8. There were 107 measurements in Class 4 control areas and 5 in Class 4 control areas, all of which met the control standards.
During the plan period, a total of 41 new adoptions were added, the length of newly adopted roads was 12.37 kilometers, and the total mileage of street cleaning was 11,043 kilometers. The ratio of road adoption pollution grades is 43% for A-grade roads (316 inspections), and 57% for B-grade roads (419 inspections)
The amount of fugitive dust generated from the particulate pollutants in construction projects was 16,981.8 metric tons per year, the total TSP generation was 4,737.9 metric tons per year, and the total PM10 generation was 2,632.2 metric tons per year. Total fugitive dust reduction was 8,970.3 metric tons/year, TSP reduction was 2,502.7 metric tons/year, and PM10 reduction was 1,390.4 metric tons/year.
The utilization rate of online declaration of air pollution charges for construction projects has reached 92.9%, and 2 briefing sessions have been held. The first briefing session was attended by a total of 46 people, including 39 construction owners (organizations) (29 units), The development unit (civilian) is 7 people. A total of 38 people attended the second briefing session, including 12 construction owners (developers) and 26 contractors.
|