中文摘要 本計畫執行期間自97年度1月至12月,計畫執行對象為具廢機動車輛受補貼機構資格之回收機構(以回收機構之稽核認證場所區分,屬基隆市(含)以南、台中縣(含)以北及宜蘭縣、南投縣地區),廢機動車輛稽核認證須分別執行引擎查驗稽核認證及廢車殼雜質查驗稽核認證作業。共計執行3,322場次稽核認證,其中引擎稽核認證為802場次,廢車殼雜質查驗為2,423場次,而其他相關認證場次為97場次。共計97年1月至12月廢汽機車回收量為255,491輛,廢汽機車處理量為230,077輛;廢車殼清運稽核共55,027,126公斤。 此外,本計畫亦完成合約書所規範之各項作業,包括回收量、處理量稽核、作業程序稽核、環境查核、定時繳交各類認證文件、成果報告、工作分析以及手冊修訂、並依照稽核認證作業手冊所訂之時程上網登錄稽核行程、新設廠及變更審核、異常事件處理、衍生物流向查核、清淨家園等作業。再者,本計畫已建置完成各項作業作業程序書,以確保執行品質,亦包括內部稽核、品德管考、績效評估以及人員教育訓練等。藉由前述各項工作之執行,本計畫已達成97年度之執行目標。
中文關鍵字 回收量, 處理量稽核, 補貼費用

基本資訊

專案計畫編號 EPA-97-HA14-03-D024 經費年度 097 計畫經費 23000 千元
專案開始日期 2008/01/01 專案結束日期 2008/12/31 專案主持人 伍中流
主辦單位 回收基管會 承辦人 盛茂仁 執行單位 台灣檢驗科技股份有限公司

成果下載

類型 檔名 檔案大小 說明
期末報告 廢機動車輛類-北區(期末定稿含附件).zip 11MB [期末報告]公開完整版

The Auditing & Certification Project of The Regulated Recyclable Waste(Wast Vechicle-North)

英文摘要 This project was carried out from January to December of 2008 and the object of this project to be executed is the waste vehicle recycling agencies with the qualification of being got subsidy (divided into Keelung City with downward its south area, and Taichung County with upward its north area, Yilan County, and Nantou County). The auditing and certification for waste vehicle must be executed separately examinations on engine and the impurities of waste body shell. We administer the auditing and certification 3,322 times in total. There are 802 times on engine examination and 2,423 times on the impurities examination. And other related examinations are 97 times. From January to December of 2008, in total of 255,491 waste vehicles were recycled; 230,077 waste a vehicles were disposed. And 55,027,126 kg of waste body shell in total were cleaned, transported, and audited. In addition, this project also completed various tasks specified in the contract, including recycled and disposed quantities audit, operation procedure audit, environment examination, regular submittal of various accreditation documents, result report and revision of manual and etc. Besides, according to the schedule specified in Audit Accreditation Operation Manual, the audit schedule had registered on the internet, including handling of abnormal cases such as assisting new plant application and modifying audit, and handling exceptional cases, examining where the derivatives flow to, cleaning the homeland and etc. Furthermore, this project has established the operation procedure manual of various operations in order to ensure execution quality, including internal audit, character management and assessment, performance evaluation, and personnel education and training. With the execution of abovementioned tasks, this project has achieved the goal of the execution in 2008.
英文關鍵字 Recycling amounts and processing amounts auditing, Subsidy