1.The quantification work carries out the progress
This plan on July 19 carries out from 99 years to 100 years on July 18 stops, total completes each kind to build the work site pollution control to check does an inspection 12,433 times, each kind builds the work site pollution control to do an inspection 9,340 times (to do an inspection 226 times including holiday), the third-level project and the path, the pipeline project does an inspection 2,816 times (to do an inspection 42 times including holiday) and the coordinate environmental protection bureau personnel examines reaches 277 times.
2.Builds the project to do an inspection to control
This plan execution period, in the construction the work site calculates has 5,322 work sites (first-level work site 1,768, second-level work site 2,583, third-level work site 971). The first-level work site accepts the tube rate to reach 95.2%, the second-level work site accepts the tube rate to reach 92.7%. Last time checks the result according to this plan, every quarter the first-level work site managed the coincidence rate respectively is 61.4%, 83.9%, 85.1% and 88.9%. Builds the work site TSP reduction rate present situation is 51.01%; Altogether accuses according to the spatial dirt method punishes 39, is the spatial dirt method 23rd 2nd item of institute subscribes the policing method case idea to have 19, the total improvement has completed, the improvement finish rate is 100%.
3.Builds the work site counselling work
Before this plan altogether completes the operation, to counsel 42 inferior work site, the counselling object architectural engineering and other projects primarily, architectural engineering - RC is 24 times (accounts for 57.1%); The other project 10 times (account for 23.8%). Recognizes raises the path to wash sweeps builds the project to have 52, washes sweeps the road section to amount to 68, always recognizes raises washes sweeps the length is 43,734 kilometers, goal agreement rate is 100%. Washes according to the environmental protection bureau path sweeps the TSP decrement coefficient 0.0138 tons/kilometer to push estimates, this work may reduce 603.5 ton TSP.
This plan execution period, altogether carries out plan of the 16 project coordination implementation spent clay landing, this plan main execution way including 9 work site choice folk recipe direct excavation to transport vehicle on, 7 work site choice use airtight container - too empties.
This plan carries out 9 work sites to build the work site in addition exposed to plant lives or the beautification, the area amounts to 16.9 hectares, after pushing estimates plants before death, reduction rate approximately is 64%; Carries out 15 to build the work site contractor to sign “the pipeline project to use the low dirty dyer law”, and completes checks and photographs the evidence, before pushing estimates uses the low dirt dyer law, the withdrawal is 11.8 tons, after the carrying out, is 5.6 tons, reduction rate 47.9%.
This year in view of the hectare high beach exposed carries on located at nearby big tree area Taiwan 21st province Confucian orthodoxy range road 10th exposed reduces the improvement characteristic work, plants the vine peanut and the green cypress grass in above, and is close to the local water source by the gravity way interception to carry on the irrigation. Pushes estimates this job cut rate to be possible to reach above 45%.
4.TSP, oil quality and noise examination work
Examination of unit this plan request environmental protection bureau approval, completes the TSP sampling to examine 10 spots time, possesses is all conformed with examination of value the rodman place the emission standard, the average examination value for 204μg/Nm3. In recent years the TSP examination's fraction defective dropped gradually, the primary cause for the camp construction work many in the examination when will adopt the project to stop temporarily the way in accordance to, therefore TSP of test result the present stage has been unable to respond the work site present situation, suggested that the environmental protection bureau will urge in view of the shoe not to listen to it in the future to build the work site, will cite the spatial dirt method 31st pollution behavior to accuse directly then, as for the TSP examination, then may utilize in the large-scale region develops examination of the work site.
When the oil quality sulphur content examination aspect, this year coordinates the environmental protection bureau carries on the examination work, in view of builds in the work site the construction machines and tools to carry on the oil quality sampling work, and the detailed record sampling process, altogether completes the construction machines and tools oil quality sampling to examine 40, is examined the machines and tools including the excavator, the bulldozer, the generator and the crane and so on, the test result total conforms to the laws and regulations standard.
In addition completes 10 to build the work site border noise examination, the examination value is between 56.8~69.8 dB(A)(LAeq), according to was measured that the position respective noise controls the region respectively be the second kind 70dB(A) and the third-order 75dB(A) noise control standard, is conformed to the laws and regulations standard the rodman total.
5.The guidance work and the personnel train the meeting
99 years on December 13 handles completes 1 “builds the project laws and regulations guidance to show that can”, 99 years on December 24 handle completes 1 number “the pipeline and the road engineering personnel decrement and the construction labor law showed the conference”, 100 years on March 15 handles completes a number “to build the work site environmental protection personnel education and training meeting” and 100 years on May 20 handles completes a number of “technical order the river sparse project cross county city to be able”. The conference builds the project management means besides the guidance, in addition builds the project control achievement after the county city merge, also one and showed to the attending personnel. What is worth paying attention is of technical order the river sparse project cross county city can handle for the first time for this city all previous years, the guidance content provides it except the broadcast by the Pingdong County government environmental protection bureau 'the air pollution against system measure SOP guidance short film', explained that against system work should result from the source, namely arranges in order the air pollution against system funds item by item from the project budget contract formulation stage, turns round carries out in the project construction establishes each item to pollute against system facility, after as well as establishment, the contractor should normal operation each item pollute against system facility. The Gaoxiong Municipal government Environmental protection Bureau also specially aimed at the river sparse project to look up in recent years (checks) project of flaw the nucleus, as well as easy to produce raises situation of the dust, proposed specially it polluted establishment of standard and the operating mode against system facility, simultaneously also aimed at the car dealership way and exposed reduces the characteristic improvement, proposed the innovation labor law.
6.Builds the project spatial dirt to spend the collection work
Plan execution period builds the project new declaration case, the idea has 4,420, after 30 spatial dirt spend the calculation, has not surpassed 100 Yuan, therefore does not give the collection, other 4,390 actual collection amount is 59,437,616 Yuan. In the bureau pays expenses the idea to have 1,567, occupies total Shanghai to give the case proportion 35.2%; Not participating in payment is the statistics has 2,823, occupies total Shanghai to give the case proportion 64.8%, conforms to this plan contract to stipulate that not participating in payment number of articles reaches the whole year to pay above number of articles 30%.
7.The spatial dirt expense checks the work
Plan execution period altogether completes 2,863 time spatial dirty expenses to check, the operation checks is 2,396 times, occupies always checks several 83.7%; Finishes checks is 467 times, occupies always checks several 16.3%. The first level of project spatial dirt expense checks 881 times, occupies always checks several 30.8%; The second level of project checks 1,443 times, occupies always checks several 50.4%; The third level of project checks 537 times, occupies always checks several 18.8%; In addition checks 2 not to grade the project.
8.The spatial dirt expense exceeds the time limit the outgoing message work
Plan execution period, the statistical outgoing message number of articles idea has 107. The analysis exceeds the time limit of administrative division and the project the outgoing message do not discover that many spends the scene by the spatial dirt to check the spatial dirt expense to exceed the time limit, to build the control system to check does an inspection to record has exceeded the time limit, and the municipal government various administrative offices crosswise work checks had not reported that is the outgoing message object, various projects category exceeds the time limit the outgoing message situation, take architectural engineering as highest, altogether 88, account for 82.2%th total number of articles; Next for the road engineering and other projects, each is 8, accounts for 7.5%th total number of articles. Various areas of jurisdiction exceed the time limit the outgoing message situation by Fengshan District 38 many, accounts for the total number of articles 35.5%.
9.The spatial dirt expense pays and submits the work
Plan execution period, altogether completes 448 spatial dirt expenses to pay and submit the work, pays and submits the amount is 6,715,879 Yuan. And, architectural engineering 361 most, accounts for 80.6%th total number of articles, the subject matter grasps for the construction time is not good, has phenomenon of majority of the time short message. Because the architectural engineering reported that the construction time is mainly proposed by the owner, indicated built the entrepreneur and the contractor grasps the nature to the project progress still to have the slight defect. The suggestion examination personnel should from the construction license the construction area, the floor appraise the construction time rationality once more, by reported by no means a personnel side recognizes the time voluntarily, reduces this time short message phenomenon to have the probability.