The beginning of this year's program the implementation of the calendar year after the first inventory of unfinished construction sites, one after another self-build project Air Pollution Control Fee Construction Engineering Group has the basic information (93 to 97/12/31 only) of 4129 pens, screening has been completed After the site there are 792 sites, the out pipe emissions of a larger site to the project, has the risk of pollution, the people who petitioned the EPA action and the air quality station near the main site. In addition, in the protracted (Tour) to control the process undeclared air pollution control fee reported to the Environmental Protection Agency site inventory audit group call charges. This year a total of the actual inspection tube 715 construction site.
According to various types of construction works area statistics show that this year the construction site of a total area of 440,460.91 square meters, of which the public has major projects 16 provision of the Eastern works, stormwater drainage works Wufeng South Road (second level), National Institute of South China High commercial vocational school classrooms new construction, new construction, Chiayi Industrial High classroom; Western National Memorial Park has 228 new construction (earthworks), National Road No. 1 S 5315 Road, Chiayi communicate contact Road project, new construction RT-Mart, Chiayi, Chiayi City Lake pumping station and associated drainage works (b) pumping stations, 228 new works to commemorate National Park (visitor center, and toilet), stone-building Corp. stores, such as housing new construction project. The city's main sources of pollution load for the RC building, roads and other projects, accounting for the city's TSP emissions in the 83.7 percent, it plans to control-oriented focus of this year because the public has 16 major projects such as the provision of works to carry out operations, so other works of TSP emissions for 129.71 tonnes, account for Chiayi City TSP emissions of 37.1%. Through the program staff to strengthen the inspection and control, this year's TSP produced 349.22 tons of reduction in volume of 175.16 metric tons, the reduction rate of 50.2%.
In the database file can be divided into clerical work files, computer files second part of the database, the following will summarize Description:
1. Instruments archives
Archives data, divided into four parts: A. the construction site information B. Information C. contractors contracting unit D. Tracking control information data. Contractors and contracting units which information is more pure, respectively, to cover their basic information and the jurisdiction or contractor of the site, as to the construction site has information includes basic information, engineering, operating hours Record Table, pollution protracted (Tour) check Record Form and delay (Tour) to check the lists.
2. Computer database
Computer files related to job database rather complicated, that they cover the range of instruments in addition to file data input file, the query can be the implementation of information, statistics, emissions estimates and statements print functions. In addition, the computer file needed to be a huge number of electronic photo albums, according to control number and date of a complete set up computer files.
In the coordination of operations, this year has completed four ACC, invited by the object to create works for the city and school authorities and other units. Will attend the first coordination number of 15 people (the number of units sent 18 / attend the 83 percent ratio), the second co-ordination number of 18 people will attend (the number of units sent to 20 / to attend the ratio of 90%). The third co-ordination number of 24 people will attend (the number of units sent to 39 / to attend the ratio of 56.41%), will attend the fourth co-ordination number of 13 people (the number of units sent to 25 / to attend the ratio of 52%).
The goal of the job this year with the completion of several cases in detail in table -1 and Fig pick picking -1, a summary of the results of the work are as follows:
1. The inspection tube 715 of the construction site.
2. According to management practices on site grading standard tube, for the site listed in the tube to complete the protracted (Tour) to 2037 times, and reached 101.9 percent target.
3. Set up the site database 2037 pens, each site has information includes basic information, investigate the status of operation and control and inspection of each record.
4. A total of 4 shows the coordination of operations.
5. This year's new return tube 519 sites, 10 sites were selected to conduct counseling, has completed implementation of 10 experts and scholars on site counseling and guidance to the scene to track operations, and conduct follow-up tracking of counseling.
6. By verifying the (Tour) to control the scene counseling or telephone follow-up counseling Tatsu pollution to improve the ratio of 100%.
7. In the inspection program under the control of delay, the site for violating the Waste Disposal Act of disciplinary actions against five persons, in violation of Air Pollution Control Act of disciplinary actions against four persons, for a total of nine prosecution action has been completed to improve and strengthen follow-up inspections to control the delay.
8. The plan to 97 the annual total oven control dust emissions from the front row for the 1251.69 tonnes of heavy volume, reducing capacity of 627.82 metric tons, the reduction rate of 50.16%. TSP emissions from the front volume control for the 349.22 metric tons, the reduction amounted to 175.16 tonnes, PM10 control volume for the front row of 194.01 metric tons, the reduction of 97.31 tonnes.
9. This year's statistics from December 31 only, the city's Air Pollution Control of Construction Engineering to declare the number of total charges for 519, to declare a total amount of 4,069,200 yuan, paid 4,670,217 yuan, 53,477 yuan deducted from refund total amount paid-up 4,616,740 yuan. Which to the Western site of the city to have to pay a higher proportion of 116%, and to pay a rate higher than 100% due to some construction work required by the settlement to pay after the air pollution fee, so paid-up amount is higher than the declared amount.
10. The plans for the upgrading of the implementation of the effectiveness of the site for the city to beautify the green fence, the year completed the counseling green landscaping fence 30, which has 22 sites of the purposes of fence on the ads to promote the implementation of a construction site fence painting, 3 site and advertisement purposes fence green fence and landscaping, has seven sites in order to plant flowers to beautify the green way.
11. The plans were ongoing to check and counseling of 11 do not waste earth landing operations, one after another to track its follow-up to backfilling, the laying of track to inspect the situation of a total of 20 times, and the model for other sites in order to promote the effectiveness, counseling counseling owners will be replaced by CLSM (plasticity of low-intensity) in lieu of backfill grouting earthwork in order to safeguard the quality of the road environment.
12. The counseling program completed a total of 22 construction site, or completion of the exposed part of green vegetation, a total implementation of green practices green vegetation on the site of its area of 36995.2m2.
13. Total completion of this project to adopt aspects of the road 10, for a total length of 6.62 kilometers adoption, implementation of the cumulative length of 799.37 kilometers of street washing and sweeping the streets the length of 293.86 kilometers, the road adopted by units of the street cleansing operation to implement the reduction of 11.03 tonnes of TSP , 2.08 tonnes of PM10, and sweep the street to reduce the volume of 4.06 tonnes for the TSP, 0.76 tonnes of PM10.